Weekly Construction Update June 17

road construction

Various Counties

I-15, Cable Barrier & Guardrail

Contract:

Meadow Valley Contractors (Multiple Locations)

Amount:

$2,815,200

Location:

Southern Utah

Impact:

* Shoulder closures – No significant traffic impact.

Activity:

* Installing cable barrier.

* Installing guardrail.

Washington County

I-15, Black Ridge to the Iron County Line

Contract:

W.W. Clyde & Co.

Amount:

$17,338,995

Location:

Between the Toquerville and New Harmony exits.

Impact:

* Consecutive lane closures at Exits 40 and 42.

* Lane merging slow downs.

* Lane shifts to accommodate paving and grading and structural work.

* Nightly lane closures.

Activity:

* Paving

* Drainage structures from mileposts 36 to 38 northbound.

* Preparing new pavement section at New Harmony and Kolob Canyon Exits.

* Fence and sign installation.

I-15, Dixie Drive Interchange

Contract:

Washington County Constructors

Amount:

$52,549,452

Location:

St. George (Mileposts 5 – 6)

Impact:

* Two lanes of traffic remain open in both directions.

* All exits are open.

* Speed is reduced to 55 m.p.h.

* Northbound traffic has been shifted to the southbound side of the interstate near the Santa Clara bridge.

* Traffic lanes have been shifted on Hilton Drive.

* The Hilton Drive Trail is closed.

Activity:

* Retention walls west of I-15.

* Flood debris removal and dredging.

* Electrical line work.

* Paving preparation on Convention Center Drive

http://www.udot.utah.gov/i15dixie/

S.R. 212, Telegraph Street

Contract:

Interstate Rock Products

Amount:

$5,515,140

Location:

City of Washington, 500 West to 300 East

Impact:

* Traffic lanes weave through the project.

* Reduced speeds.

* One lane of traffic in each direction.

* Sidewalk closures.

Activity:

* Storm Drain installation on west end.

* Backfilling at bridge.

* Sub-grade work from Main to 300 East.

* Installing curb and gutter near Main Street.

S.R. 59, Arizona State Line to Apple Valley

Contract:

A-T Asphalt Paving

Amount:

$1,998,101

Location:

Mileposts 0 to 11

Impact:

* Oversized loads restricted.

* Pilot car operations with delays of up to 15 minutes.

Activity:

* Paving.

Southern Parkway Advanced Traffic Management

Contract:

Transcore ITS

Amount:

$370,674

Location:

S.R. 7 Mileposts 0 to 7

Impact:

* No traffic impacts.

Activity:

* Fiber optic installation, junction boxes, camera foundations.

Carbon County

S.R.10 South Price to Stake Farm Road

Contract:

Nielson Construction

Amount:

$1,840,710

Location:

South of Price

Impact:

* No major impacts expected.

Activity:

* Construction Preparation.

* Work will begin on the south end near Stake Farm Road

* Construction Open House June 23rd from 4 to 7 p.m. at the Holiday Inn in Price.

Emery County

U.S. 6, Milepost 272 To Woodside

Contract:

Nielson Construction

Amount:

$3,869,924

Location:

22 Miles north of Green River

Impact:

* Narrow lanes.  One in each direction.

Activity:

* Paving.

Grand County

I-70, Yellowcat to West Cisco

Contract:

Geneva Rock

Amount:

$2,255,629

Location:

East of Thompson Springs Welcome Center

Impact:

* Single lane closures in both directions.

Activity:

* Paving.

Free News Delivery by Email

Would you like to have the day's news stories delivered right to your inbox every evening? Enter your email below to start!

Posted in News

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.