I-15, Black Ridge to the Iron County Line
Contract: W.W. Clyde & Co.
Amount: $17,338,995
Location: Between the Toquerville and New Harmony exits.
Impact: * Potential single lane closures both directions at the bridge over Exit 42.
* Lanes shift to accommodate excavation work.
Activity: * Structural work continues on exits.
* A box culvert is being extended at milepost 42. .
* Fence installation is ongoing.
* Workers are installing conduit.
* Heavy equipment operators are excavating and moving material in the median and shoulders.
I-15, Dixie Drive Interchange
Contract: Washington County Constructors
Amount: $52,549,452
Location: St. George (Mileposts 5 – 6)
Impact: * Two lanes of traffic remain open in both directions.
* All exits are open.
* Speed is reduced to 55 m.p.h.
* Northbound traffic has been shifted to the southbound side of the interstate near the Santa Clara bridge.
* Motorists should use caution near the Bluff Street Interchange merge lanes.
* Traffic lanes have been shifted on Hilton Drive.
* The Hilton Drive Trail is closed.
Activity: * Pouring concrete for the new northbound I-15 bridge over the Santa Clara River, and various structures.
* Paving the northbound off-ramp.
* Retention walls west of I-15 and also under the Bluff Street Interchange.
* Structural preparation for the future southbound on-ramp.
* Drainage work at Hilton Drive.
* Flood debris removal and dredging.
http://www.udot.utah.gov/i15dixie/
S.R. 212, Telegraph Street
Contract: Interstate Rock Products
Amount: $5,515,140
Location: City of Washington, 500 West to 300 East
Impact: * Traffic lanes weave through the project.
* Reduced speeds.
* One lane of traffic in each direction.
* Sidewalk closures.
Activity: * Curb and gutter installation.
* Storm drain installation.
* Road milling on the north side of the road from 300 West to 100 West.
* Bridge work.
S.R. 9, 300 West To 800 North Hurricane
Contract: Interstate Rock Products
Amount: $10,203,871
Location: Hurricane City State Street
Impact: Expect single lane closures.
Activity: * Paving is expected to resume.
* Manhole work.
Southern Parkway Advanced Traffic Management
Contract: Transcore ITS
Amount: $370,674
Location: S.R. 7 Mileposts 0 to 7
Impact: No traffic impacts.
Activity: Conduit installation, junction boxes, camera foundations